Pipeline
Underground Projects
   
     Pipeline

Underground Projects
Pipeline
Cable and Conduit
Gas Distribution
Water and Sewer
Horizontal Directional Drilling
Printable Version

Kern River Pipeline

The Kern River Gas Transmission decided to expand the existing Kern River gas pipeline by 700 miles. ARB, Inc. successfully bid on Spread 10 of the Kern River gas pipeline. Spread 10 consisted of 82 miles of 42-inch pipe, while all other spreads required 36-inch pipe, The larger diameter pipe gave ARB, Inc. the greatest challenge of the expansion. ARB met the challenge and completed the project in only four months. The Kern River gas pipeline begins in Wyoming and ends in California, and will provide 900 million cubic feet per day of natural gas. The new pipeline was severely important to provide the increasing need for natural gas. The original pipeline has been running at 100 percent capacity for a few years, and the federal government recognized the importance of the expansion and permitted the project in record time. All the crews and equipment where allowed on the right-of-way only one week prior to the start of the job, because of permitting.


ARB had to review every detail of the pipeline and prepare for the worse. The equipment demand for a project of this scope was gigantic, and before the project start-up ARB mobilized 300 pieces of equipment. Three-quarters of the equipment used was owned by ARB.


Daggett to Mojave, California The pipeline went through many environmental, and archeological sensitive areas. ARB employees were trained about the sensitivity of the region and the proper procedures incase a situation were to arise. Monitors were placed with every crew along the right-of-way to guarantee a project with minimal disturbance to the area. Over 500 employees worked on the pipeline, including local labor. All employees had to go through safety instruction and drug testing implemented by Williams and additional training required by ARB. Safety is always a priority of ARB. With a pipeline of this size and working to meet a deadline, safety of all employees was a huge concern. The terrain of the project ranged from mountains to river beds. The trench had to be a minimum of 7 feet deep, and the majority was dug using two large trenchers cutting a 60-inch ditch. ARB had 23 directional drills under highways and railroad crossings, all completed with a brand new 60-inch boring machine. Automatic Welding Systems attached to pipelayers, where used to provide rapid accurate welding along the pipeline.


Additional Photography
Documentation
INDUSTRIAL GROUP UNDERGROUND GROUP
  Copyright ARB INC 2004 © designed by ahdfx